MSP begins a new week on Saturday at 2:00 PM instead of 12:00 AM on Saturday. Generally, we have found that this is the way most of the churches we work with would like their services to be grouped. However, you can control this option when exporting a schedule in any view that can be grouped by week. 

1. Go to File - Export Schedule

2. In the Layout Settings pane, look for the checkbox that says "Group services together by week"

3. Where it says "(Start week: Sat 2:00 pm)" click the blue link

4. Reset the start of the new week to the day (Saturday or Sunday) and time you want

5. Click OK and Export Schedule

 